CAMP FAR WEST HYDROELECTRIC PROJECT RELICENSING
FERC NO. 2997

Calendar

Aug 01, 2020

FERC issues additional AIS, if necessary - August 2020

Category: General FERC issues additional AIS, if necessary - August 2020

N/A
Aug 01, 2020

FERC's June 9, 2020 Scoping Document 1 provided target months for these relicensing milestones. SSWD will update these dates if FERC provides more clarity but is not responsible for a third-parties filings.

FERC issues Notice of Ready for Environmental Analysis (REA) - August 2020

Category: General FERC issues Notice of Ready for Environmental Analysis (REA) - August 2020

N/A
Aug 01, 2020

FERC's June 9, 2020 Scoping Document 1 provided target months for these relicensing milestones. SSWD will update these dates if FERC provides more clarity but is not responsible for a third-parties filings.

FERC issues Scoping Document 2 (SD2), if necessary - August 2020

Category: General FERC issues Scoping Document 2 (SD2), if necessary - August 2020

N/A
Aug 01, 2020

FERC's June 9, 2020 Scoping Document 1 provided target months for these relicensing milestones. SSWD will update these dates if FERC provides more clarity but is not responsible for a third-parties filings.